Upgrading of overhead traveling crane capacity require, in most cases, replacement or reinforcement of the existing crane runway girders.
Replacement of the girder is the most expensive alternative. It can only be implemented when the girder reinforcement is physically impossible or more costly than the girder replacement.
Crane girder reinforcement is a challenging task for the design engineer. It involves not only a girder reinforcement design lo meet strength and serviceability criteria, but also problems such as downtime in the crane operation to construct the ·reinforcement, interference with existing structures and equipment, and modifications of element attached to the girder (eg, walkways , hot rails, piping, electrical conduit supports, etc).
Conventionally, an increase in the crane lifting capacity require an increase of the crane runway girder vertical and horizontal section properties to satisfy biaxial bending criteria under the action of the increased crane vertical and horizontal loads. In addition, if vertical web shear design stresses exceed allowable, the girder web shall be reinforced.
Reinforcement of the girder top and bottom flanges is labor and time-consuming. The top flange reinforcement, in most cases, requires the removal of the crane rail, which means an extended downtime in the crane operation. A continuous -welded or bolted attachment of the reinforcement parts to top and bottom flanges is extremely costly from a labor point of view.
If a substantial increase in the crane lifted load is considered, the total cost(fabrication and field work) of a conventional method of crane girder reinforcement could exceed the cost of girder replacement.
A nonconventional approach, described in this article, includes two alternative methods of crane girder reinforcement. They allow a substantial increase in the crane lifted load and a significant reduction in the scope of the field work required to install the girder reinforcements The two alternative methods are:
- Girder conversion into a truss-type structure.
- Crane load sharing between a crane girder and a beam installed below the crane girder
Both of these methods are based on the concept of breaking the girder span into two or more continuous spans that are then supported by the elastic spring in the girder sections. In both cases, a design engineer can determine the optimum stiffness of the elastic spring to achieve both the desired crane girder vertical bending moment and shear reduction necessary to satisfy the strength and deflection criteria under the action of increased crane loads.
An installation of the truss-type modification al o ha a positive effect on crane column s. It increases column stability against out of plane buckling which could govern the crane column design. In addition, it also reduces the crane maximum vertical load on the girder seal as a result of a shear redistribution effect. This approach to crane girder reinforcement is extremely effective for small and medium-span girders 20 to 40 R long. The only deficiency of the girder into truss conversion method is a requirement of available space below the crane girder bottom flange to install reinforcement details. If the pace below the girder bottom flange is limited, the alternative approach - the girder load sharing method is applicable.
Sizing of the reinforcement diagonals, lower chord members and support beams is performed based on an analysis of the modified girder system as an elastic frame. Utilization of a computer program with moving load features can be a convenient tool to determine a force envelope for each member of the system. By changing member sizes of new reinforcement members, the designer can achieve a desirable force distribution between the existing crane girder and new reinforcement members.
The following examples illustrate a design application of the nonconventional crane girder reinforcement approach.